ADP's unauthorized 924 projects were suspicious

প্রকাশ: সেপ্টেম্বর ২৬, ২০২৪

Eiahia Nakib

The previous Awami League government undertook many development projects. Various ministries and departments regularly approved projects that exceeded the mid-term budget ceiling. There are also allegations that projects were taken solely for political considerations and contractors' interests. In the current fiscal year's Annual Development Program (ADP), there are 1,326 ongoing projects. Additionally, another 924 projects are awaiting approval for government funding, which is the highest number in four years.

The initial cost estimation for these unauthorized projects is approximately BDT 5.5 trillion. However, given the changing circumstances, there are doubts about whether these projects will be approved. Analysts indicate that there are many uncertainties regarding the goals and objectives of these projects. Many of them have been added to the list without proper scrutiny. Several projects have been included for political purposes and under pressure. There have also been widespread allegations of corruption and embezzlement in similar projects.

Furthermore, there are instances where three-year projects have taken up to 15 years to complete due to various complications. The interim government needs to reassess these unauthorized projects and arrive at a prompt decision. It is also crucial to evaluate whether these projects are genuinely necessary.

Former professor of the Economics Department at Chittagong University, Dr. Muinul Islam, has raised questions about various mega projects during the previous government. Regarding the many projects listed in the ADP, he told Bonik Barta, “These have been included for corruption and embezzlement. The current government needs to investigate whether these projects are necessary.”

According to sources from the Planning Commission, the ADP for the current fiscal year 2024-25 includes 259 unauthorized new projects funded by foreign sources. There are also 47 projects intended for implementation through the self-financing of autonomous agencies. Additionally, there are 924 projects awaiting approval for government funding, with an initial estimated cost of BDT 5467.19 billion. In total, the number of unauthorized projects stands at 1,230. These projects have been categorized based on low, medium, and high priorities, but most unauthorized projects fall under high priority.

An analysis of the list of unauthorized projects in the ADP reveals that similar to previous years, projects in the transportation and infrastructure sectors are the most numerous. This includes projects to construct 12 separate flats in various districts, including six in Dhaka for government officials. There are also 14 projects to construct various circuit houses. Additionally, most projects in the education sector have been focused on infrastructure development.

A review by the private research organization Center for Policy Dialogue (CPD) showed that in the fiscal year 2023-24, there were 829 unauthorized projects in the ADP. In the previous fiscal year, there were 633 projects, while in 2021-22, the number was 603. This fiscal year, the number has increased to 924.

Professor Dr. Mustafizur Rahman, a distinguished fellow at the Center for Policy Dialogue (CPD), believes verifying these unauthorized projects beforehand is essential. He told Bonik Barta, “Verification of ongoing projects has already begun. It is necessary to establish new priorities for these projects.”

The highest allocation in the current year's ADP has gone to the transportation and communication sector, followed by the power and energy sector. These two sectors account for over 40 percent of the ADP allocation. While the previous government prioritized infrastructure development, the current government has announced that it will prioritize human resource development. Government advisors have also stated that special attention will be given to the education and health sectors.

Dr. Selim Raihan, Executive Director of the South Asian Network on Economic Modeling (SANEM), believes that most projects have been included for political considerations without proper verification. This professor from the Economics Department at Dhaka University told Bonik Barta, "Additional projects have been listed with the intention of corruption, which is creating a burden in the ADP. There should be a quick reassessment of these lists to reach a decision."

The government sets a financial limit for project approvals for each agency and ministry through a three-year mid-term budget framework. This policy was primarily adopted to maintain discipline in project approvals relative to financial resources. However, almost every ministry exceeds the limits set by the government when taking on projects.

Former Planning Secretary Pradip Ranjan Chakraborty said that when the limits of the mid-term budget are not adhered to, there is a shortfall in allocations for all projects. He told Bonik Barta, “When projects are pushed beyond the limits, the allocation is less than the demand. In such cases, the budget for all projects in that ministry has to be reduced.”

In the last fiscal year, the development allocation for the Ministry of Road Transport and Bridges was BDT 340 billion, while the ministry required BDT 390 billion for ongoing projects. This means that more than BDT 50 billion worth of projects were in process beyond the allocated budget for that ministry. The same pattern is observed in other ministries as well.

Former Finance Secretary Mohammad Muslim Chowdhury alleged that projects in the country are not based on financial resources. He told Bonik Barta, "Projects are forcibly added to the list through political lobbying. As a result, due to insufficient allocations, it can take up to 15 years to complete projects intended for three years. Consequently, these projects do not yield significant benefits for the nation."

He said, "A project often starts with purchasing a vehicle for the project director. Work often begins with a nominal allocation of just BDT 5 lakh. Later, these projects get dragged on for years. This is a structural issue that needs to be addressed."

According to CPD data, 1,138 of the ongoing projects are more than five years old. 357 projects have been ongoing for 6-10 years, and 36 projects have been running for over 10 years. In the current fiscal year, the timeline has been extended for 518 projects. In the previous fiscal year, the timeline for 429 projects was also extended. This indicates that the tendency to extend project timelines is increasing compared to before.

Efforts were made to contact planning advisor Wahiduddin Mahmud for a comprehensive discussion, but his comments were not immediately available. However, during the first ECNEC meeting of the interim government, Chief Advisor Dr. Mohammad Yunus stated, "The projects taken for political purposes during the previous government will be verified."

 


সম্পাদক ও প্রকাশক: দেওয়ান হানিফ মাহমুদ

বিডিবিএল ভবন (লেভেল ১৭), ১২ কাজী নজরুল ইসলাম এভিনিউ, কারওয়ান বাজার, ঢাকা-১২১৫

বার্তা ও সম্পাদকীয় বিভাগ: পিএবিএক্স: ৫৫০১৪৩০১-০৬, ই-মেইল: [email protected]

বিজ্ঞাপন ও সার্কুলেশন বিভাগ: ফোন: ৫৫০১৪৩০৮-১৪, ফ্যাক্স: ৫৫০১৪৩১৫